Our proven renovation process that prevents mistakes and delays
After 25+ years and hundreds of renovations, we’ve refined our process to eliminate the common problems that plague renovation projects. Here’s exactly how we manage your renovation from start to finish.

Every successful renovation starts with understanding your needs, lifestyle, and budget.
On-Site Visit
We visit your home to assess the current space, take measurements, and identify any potential issues.
Needs Assessment
Understanding your lifestyle, accessibility requirements, and design preferences.
Budget Discussion
Honest conversation about realistic costs and what’s achievable within your budget.
Initial Assessment
Basic layout options and design direction based on your requirements.
Detailed planning prevents costly changes and delays during construction.
Detailed Design
Working drawings showing exact layout, fixtures, and finishes.
Material Selection
Choosing tiles, fixtures, colors, and finishes within your budget.
Permit Applications
Submitting all required permits and approvals before work begins.
Final Quote
Detailed, fixed-price quote covering all aspects of the renovation.
Proper preparation sets the foundation for a smooth renovation process.
Material Ordering
All materials ordered and delivery scheduled to minimize delays.
Trade Coordination
Scheduling all trades and ensuring everyone knows their role and timing.
Site Protection
Protecting your home’s other areas from dust and damage.
Client briefing
Final walkthrough of the plan and timeline with our project manager.
Safe, efficient removal of existing fixtures and materials.
Why We Do Complete Strip-Outs
Unlike companies that “tile over” existing surfaces, we always do complete strip-outs. This allows us to address any hidden problems and ensure proper waterproofing from the ground up.
Service Isolation
Safely disconnecting water, gas, and electrical services.
Fixture Removal
Careful removal of bath, toilet, vanity, and other fixtures.
Tile and Surface Removal
Complete removal of all tiles and old waterproofing.
Waist Disposal
Proper disposal of all materials according to environmental regulations.
Installing the “bones” of your new bathroom.
Structural Work
Any required structural modifications or reinforcement.
Rough-In Plumbing
Installing new water supply and waste pipes to new locations.
Rough-In Electrical
Running new electrical cables for lights, fans, and power points.
Insulation and Backing
Installing insulation and proper backing for fixtures and fittings.
Our specialized waterproofing team takes over for this critical phase.
No Shortcuts on Waterproofing
This stage cannot be rushed. Each coat must dry for 24 hours minimum, and we test everything before proceeding. This is where most bathroom failures occur, so we take no chances.
Surface Preparation
Ensuring all surfaces are clean, dry, and ready for waterproofing.
Primer Application
Specialized primer for optimal membrane adhesion.
First Membrane Coat
First coat of blue waterproofing membrane applied.
Reinforcement
Fabric reinforcement tape at all joints and corners.
Second Membrane Coat
Second coat ensuring complete coverage and protection.
Testing and Certification
Flood testing and certification before any other work proceeds.
Professional tiling that will last decades.
Layout Planning
Calculating tile layout for best appearance and minimal cuts.
Floor Tiling
Installing floor tiles with proper falls to drains.
Wall Tiling
Wall tiles installed with precision cuts around fixtures.
Grouting
Professional grouting with appropriate grout for each area.
Installing your new bathroom fixtures and fittings.
Plumbing Fixtures
Installing toilet, vanity, taps, and shower fixtures.
Electrical Fixtures
Installing lights, exhaust fans, and electrical accessories.
Cabinet and Storage
Installing vanity, mirrors, and storage solutions.
Shower Screens
Installing shower screens and doors.
Our caulking specialists ensure every seal is perfect.
Why Specialized Caulking Matters
This is where we differ from other companies. Our dedicated caulking team ensures every seal is perfect, preventing the water damage that destroys so many renovations.
Ensuring everything meets our high standards before you take possession.
Quality Inspection
Our project manager inspects every detail of the renovation.
Testing All Systems
Testing plumbing, electrical, and ventilation systems.
Final Cleaning
Professional cleaning leaving your bathroom ready to use.
Client Walkthrough
Final walkthrough with you, explaining care and maintenance.
Warranty Documentation
Providing all warranties, compliance certificates, and care instructions.
Timeline Management
A typical RenoWarriors bathroom renovation takes 3-4 weeks, depending on complexity. We provide a detailed timeline at the start and update you throughout the process.
Demolition, rough-in work, waterproofing start
Waterproofing completion, tiling start
Tiling completion, fixture installation
Caulking, final details, inspection, handover
Experience Our Proven Process